How the gravel calculation works
- Area = length × width.
- Volume = area × depth, with all measurements in the same unit.
- Add extra: volume × (1 + extra ÷ 100).
- Weight = volume × density.
Gravel is often sold by weight (tons or tonnes), but you measure the space by volume, so density links the two. The default of 1.4 US tons per cubic yard (about 1,660 kg per m³) is a common planning figure for loose gravel. Real values typically fall somewhere around 1.2–1.5 tons per cubic yard (roughly 1,400–1,800 kg/m³), depending on the stone, its size and how wet it is. If your supplier quotes a density, enter that instead.
Choosing a depth
The right depth depends on the job. Decorative beds and garden paths are often laid 2–3 inches (5–7.5 cm) deep. Driveways and other surfaces that carry vehicles usually need a deeper, compacted sub-base built up in layers. Follow local guidance or a contractor's specification for those, because the base matters more than the top layer.
Compacting crushed stone reduces its volume, so if you will compact the gravel, allow more than the default extra. Your supplier can advise how much.
Rounding rules
- The order weight is rounded up to the next 0.25 ton (US) or 0.25 tonne (metric).
- The order volume is rounded up to the next 0.25 yd³ or 0.25 m³.
- Exact volume and weight, before extra and rounding, are shown separately.
Useful conversions
- 1 cubic yard = 27 cubic feet ≈ 0.765 m³
- 1 US ton = 2,000 lb ≈ 0.907 tonnes
- 1 ton per cubic yard ≈ 1,187 kg per m³ ≈ 74 lb per ft³